Enders Dam recoating job near completion PDF Print E-mail

By Josh Sumner
The Wauneta Breeze
Work at Enders Dam will be wrapping up in the coming days as contractors finish recoating the interior of the dam’s outlet pipe.
St. Louis-based Hartman Walsh Painting Co. was awarded the project by the Bureau of Reclamation. Their crew of painters and blasters began work on the seven-foot diameter steel conduit on May 10.
“The old coating was coming off in large pieces,” said Carl Koenig, Civil Engineer for the Nebraska-Kansas Area Bureau of Reclamation. “We knew it was no longer protecting the steel underneath the coating.”
The outlet pipe recoating process includes several phases. After spending a few days setting up equipment, the crew began blasting the interior of the pipe with 37,000 psi pressure water.

 